We don’t always catalogue our work in photographs, but on this occasion we have. In these photos, we’re proud to have designed and fabricated the support structures, the pre-assembly of 100t of kiln shells and the installation of a 34t new Tyre. In January 2023 we will be installing the new completed section in one piece, all of which is being managed and installed by Grayton.
View Grayton’s Upcoming Installation for a Valued Customer in the Cement Industry
GraytonThe project requires the pre-assembly of 22m of kiln sections – due for completion in 2023.